Last week the final boom deployment on the Cluster quartet was successfully completed when all four wire antennae on the Tango spacecraft were fully extended to a length of 44 m. This brought to an end a remarkable two-month-long sequence which involved 64 separate operations to unravel 16 booms (a record) and deploy around 700 m of wire (also a mission record). The successful conclusion of this complex process was due to the tremendous dedication and hard work of the scientists and the mission operations team in the control room at the European Space Operations Centre (ESOC) in Darmstadt, Germany. "Every step was a critical operation," said Silvano Manganelli, the ESOC engineer in charge of the 16 boom deployments. "Our first activity was to fire small pyro devices to open the doors on the booms. This was very stressful, since there was nothing we could do if this went wrong. All 16 devices worked perfectly -- an excellent achievement." "We also had to be very careful that there was no large asymmetry of the booms as they were released on opposite sides of the spacecraft," he added. "Otherwise, there would have been problems for the experiments and the spacecraft dynamics. This procedure has been done on a single spacecraft before, but never on four identical spacecraft in such quick succession." One further complication was the need to increase the spin rate of each satellite in order to deploy the last 1 1/2 m of wire. This final piece of very thin cable, to which the wave experiment's probe was attached, was released by relying upon centrifugal force to "throw" the wire outwards. "My colleagues from the flight dynamics department monitored this manoeuvre very closely, and did a remarkable job," said Mr. Manganelli. "In each case they were able to predict the effects of the deployment and then calculate the manoeuvres needed to bring the spin rate back to within a few hundredths of a revolution per minute of the nominal value." Now that they are all fully deployed from the spinning satellites, the booms will sweep out a giant circle in the electrified gas (plasma) around each spacecraft and provide a flood of data for the five instruments within the Wave Experiment Consortium (WEC) on each Cluster satellite. "My colleagues and I want to thank everyone at ESOC, particularly Silvano, for all their hard work," said a delighted Per-Arne Lindqvist, Chairman of the WEC. "We really appreciate the support given to us during this long deployment campaign." Related Links Movie showing antenna boom deployment (513 kb .mpg) The instruments onboard Cluster ESA Science News SpaceDaily Search SpaceDaily Subscribe To SpaceDaily Express ![]() Paris - September 11, 2000 ![]()
|
![]() |
|
The content herein, unless otherwise known to be public domain, are Copyright 1995-2016 - Space Media Network. All websites are published in Australia and are solely subject to Australian law and governed by Fair Use principals for news reporting and research purposes. AFP, UPI and IANS news wire stories are copyright Agence France-Presse, United Press International and Indo-Asia News Service. ESA news reports are copyright European Space Agency. All NASA sourced material is public domain. Additional copyrights may apply in whole or part to other bona fide parties. Advertising does not imply endorsement, agreement or approval of any opinions, statements or information provided by Space Media Network on any Web page published or hosted by Space Media Network. Privacy Statement All images and articles appearing on Space Media Network have been edited or digitally altered in some way. Any requests to remove copyright material will be acted upon in a timely and appropriate manner. Any attempt to extort money from Space Media Network will be ignored and reported to Australian Law Enforcement Agencies as a potential case of financial fraud involving the use of a telephonic carriage device or postal service. |